Our method
A data project rarely succeeds on technology alone.
It succeeds when the business rules get written down, when access arrives on time, and when acceptance testing was planned for. Here is how we run a project, and what we will ask of you, so that you can plan for it.
- Phases, from scoping to handover
- 7
- Peaks of load for your teams
- 3
- Of scoping to get started
- 2 h
- Expert consultants
- 11
- 7
- Phases, none of them skipped
- 3
- Moments that genuinely mobilise your teams
- ½ h
- Weekly check-in between those moments
- 2 h
- Free scoping workshop before any quote
Our experience
The three things that make a project work
We have run data projects long enough to see the same causes come round. None of them is technical.
The first is access to the data. The project is approved, the budget is voted, and it takes six weeks to obtain a service account on an ERP nobody remembers administering. We now ask for the access inventory before writing a line.
The second is the gap between written rules and applied rules. Margin is defined in a 2019 procedure; management accounting has computed it differently since 2022, in a workbook that never left one desk. Both figures are defensible. Someone has to decide, and it is not for us to do it, but it is for us to make the gap visible.
The third is acceptance testing treated as a formality. A report nobody has checked against their own figures is not a delivered report: it is a report waiting to be challenged. Acceptance is the moment a project wins or loses its credibility, and it has to be prepared.
The sequence
Seven phases, and what each one costs you
Your share of the work is not spread evenly
It concentrates on three moments. Knowing them in advance means booking the right people in the right weeks, and it is the leading cause of slippage when it is not done.
2-M shareYour share
Scoping
2 hours
50 % pour vous · 50 % pour nous
Your stakes, your sources, your volumes. Nothing to prepare, we listen.
Access and inventory
3 to 5 days
65 % pour vous · 35 % pour nous
The most demanding moment for you: opening access, identifying the right contact for each system, finding out who holds which password.
Data foundation
1 to 4 weeks
5 % pour vous · 95 % pour nous
Extraction, history, raw layer. We work, you get on with your day.
Business rules
1 to 3 weeks
40 % pour vous · 60 % pour nous
The second peak. The rules are written nowhere: they live in the heads of your management accountants, and they have to be drawn out.
Model and reports
2 to 6 weeks
15 % pour vous · 85 % pour nous
Semantic model, measures, reports. Short weekly check-ins.
Acceptance
1 to 2 weeks
70 % pour vous · 30 % pour nous
The third peak, and the most important: your teams compare the figures with their own. A gap found here costs a hundred times less than a gap found in production.
Handover
2 to 5 days
45 % pour vous · 55 % pour nous
Training, documentation, keys handed over. You must be able to change a report without us.
What we will ask of you
The list, given up front
These six items decide when the project can start. Gathering them usually takes longer than expected, which is reason enough to begin now rather than after signature.
Read access to each source system
One contact per system
Your current reports, imperfect as they are
Someone to arbitrate definitions
Two or three business testers
Your volumes, in orders of magnitude
The relationship
Fixed price or time and materials: what each really implies
The question comes up every time, and it is often settled for the wrong reasons. A fixed price reassures because it fixes an amount; it also fixes a scope, and anything outside it becomes an amendment. Time and materials worries people because it shows no total; it also leaves the freedom to change your mind in week four, which almost always happens.
Our position fits in one sentence: agile while the scope is moving, fixed price once it is settled. Many of our projects start on time and materials for the scoping and the inventory, then switch to a fixed price once the sources are known. That is the only moment a fixed price can be right. Our billing model in detail.
We never quote a fixed price on the basis of a description alone. A quote drawn up without opening the data is a gamble, either at your expense or at ours, and in both cases the relationship suffers before it has even begun.
Going further
The pages that detail each step
- MigrationData migrationMoving history out of Business Central, Nav, SAP or Sage without losing it on the way. Reconciliation, consistency checks, variances owned.
- Data platformMicrosoft FabricThe architecture these seven phases produce: raw, reconciled, modelled, and why that cut holds up over time.
- First stepScoping workshopTwo free hours to look at your sources and tell you what we would do. Even when it is not with us.
Frequently asked
What people ask before starting
How much time will our own teams have to spend on this?
Do you work on a fixed price or time and materials?
Can you take over a project someone else started?
What if our business rules are written down nowhere?
What if we want to take over afterwards?
The first step
Two hours, minute by minute
Twenty minutes on your systems, forty on how your figures are calculated, thirty on the architecture we would put in place, thirty on the sequence and the load on your teams. Nothing to prepare on your side.
Let us start by looking at your sources.
Eleven expert consultantsSaint-Priest, near Lyon, France
Two hours with a consultant, free of charge and with no commitment. We look at your systems, your business rules and your volumes, and we tell you how we would run the project: the sequence, the load on your teams, the friction we anticipate.
Request a scoping workshopScoping workshop · 2 hours · free · near Lyon or remote